PK0-005 Project Management Concepts Practice Question
A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Hybrid life cycle
A hybrid methodology combines predictive and agile elements, often using predictive for planning and agile for execution.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Hybrid life cycle
Why this is correct
Hybrid combines predictive and iterative approaches.
- ✗
Iterative life cycle
Why it's wrong here
Iterative implies repeated cycles, but hybrid includes sequential phases.
- ✗
Predictive life cycle
Why it's wrong here
Not fully predictive due to iterative development.
- ✗
Adaptive life cycle
Why it's wrong here
Adaptive is purely agile, not hybrid.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.