Courseiva

PK0-005 Project Management Concepts Practice Question

A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?

⚠ Common exam trap

PK0-005 often tests the confusion between hybrid and iterative or adaptive life cycles, so candidates must identify the explicit combination of predictive and iterative elements as the defining characteristic of hybrid.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Hybrid life cycle

A hybrid life cycle combines predictive and adaptive elements, using a predictive approach for some phases (e.g., requirements and design) and an iterative or agile approach for others (e.g., development sprints). The scenario explicitly describes predictive requirements gathering and design with iterative sprints for development, which is the definition of a hybrid life cycle. Therefore, hybrid is the correct answer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Hybrid life cycle

    Why this is correct

    A hybrid life cycle combines predictive and adaptive phases within one project, matching the stem's split: predictive requirements gathering and design, then iterative sprints for development. It satisfies the constraint that both approaches coexist sequentially, rather than the whole project following a single methodology.

  • ✗

    Iterative life cycle

    Why it's wrong here

    An iterative life cycle repeats cycles to refine a single deliverable through progressive elaboration, whereas this project baselines requirements and design predictively and only develops in sprints. It tempts because sprints are iterative, and would be correct if the team were refining requirements or design through repeated cycles rather than fixing them before development.

  • ✗

    Predictive life cycle

    Why it's wrong here

    A predictive life cycle runs sequentially with a single delivery at the end, so it cannot accommodate the iterative development sprints described. It tempts because requirements gathering and design are handled predictively, and would be correct if the entire project, including development, followed one planned sequential pass with no sprints.

  • ✗

    Adaptive life cycle

    Why it's wrong here

    An adaptive life cycle is fully agile, with requirements emerging and changing throughout; here requirements and design are fixed predictively, so only development is iterative. It tempts because the sprints look agile, and would be correct if scope were also discovered and reprioritised incrementally rather than baselined up front.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.