Courseiva
easyMultiple Choice

PK0-005 Practice Question: A project schedule is displayed as a bar chart…

A project schedule is displayed as a bar chart showing tasks against a calendar. Which tool is being used?

⚠ Common exam trap

It's easy for candidates to confuse a Gantt chart with a PERT chart or network diagram, as both involve task relationships, but only the Gantt chart is a bar chart against a calendar.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Gantt chart

A Gantt chart is a bar chart that displays project tasks against a calendar, showing start and end dates, dependencies, and progress. This matches the description in the question, making option B correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    PERT chart

    Why it's wrong here

    A PERT chart is a network diagram using three-point estimates to show activity dependencies and expected durations, without calendar bars. It tempts because it also depicts schedule, and it would be correct when the question asks for probabilistic duration estimation across dependent activities.

  • ✓

    Gantt chart

    Why this is correct

    A Gantt chart presents tasks as horizontal bars plotted against a calendar timeline, directly matching the stem's description of a bar chart showing tasks against dates. This format also exposes task durations, start and finish dates, and dependencies, which is precisely what the schedule display requires.

  • ✗

    Network diagram

    Why it's wrong here

    A network diagram shows tasks as nodes with logical precedence arrows, not duration bars against dates. It tempts because it also models schedule logic, and it would be correct when the question asks how activities relate sequentially or where the critical path is calculated.

  • ✗

    Work breakdown structure

    Why it's wrong here

    A work breakdown structure decomposes deliverables into hierarchical components; it carries no calendar axis or task durations. It tempts because it also organises project scope, and it would be correct when the question asks how scope is decomposed into manageable work packages.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.