Which document contains all identified risks, their probability and impact, and planned response strategies?

⚠ Common exam trap

PK0-005 often tests the distinction between the risk register (future uncertain events with probability/impact) and the issue log (problems that have already occurred), causing candidates to confuse the two.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk register

The risk register is the project management document that catalogs every identified risk along with its assessed probability, potential impact, and the planned response strategy (avoid, transfer, mitigate, or accept). It is a living artifact updated throughout the project lifecycle as risks are identified, re-evaluated, or closed. This is the standard output of the Identify Risks and Plan Risk Responses processes in PMBOK.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Change log

    Why it's wrong here

    A change log records requests, approvals and implementation status of modifications to baselines, not risk probability, impact or response strategies. It is tempting because changes often stem from risks, but the risk register is the artefact that documents identified risks and their planned responses.

  • ✗

    Issue log

    Why it's wrong here

    An issue log tracks problems that have already occurred and their resolution owners, not future risks with probability, impact and response plans. It is tempting because issues and risks are often managed together, but only the risk register holds identified risks and their planned responses.

  • ✗

    Project charter

    Why it's wrong here

    The project charter authorises the project and names the sponsor, objectives and high-level scope; it does not catalogue every identified risk with probability, impact and response strategies. It is tempting as the initiating document, yet risk detail belongs in the risk register, which is maintained throughout delivery.

  • ✓

    Risk register

    Why this is correct

    The risk register is the artefact that logs each identified risk alongside its probability, impact and agreed response strategy. It satisfies the stem directly, unlike a risk management plan, which describes approach rather than listing individual risks.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.