PK0-005 Project Life Cycle Practice Question
Which document contains all identified risks, their probability and impact, and planned response strategies?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk register
The risk register is the central repository for risk information throughout the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Change log
Why it's wrong here
Change log tracks change requests.
- ✗
Issue log
Why it's wrong here
Issue log tracks current issues, not risks.
- ✗
Project charter
Why it's wrong here
Charter authorizes the project.
- ✓
Risk register
Why this is correct
Correct: The risk register contains risk details.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.