PK0-005 Tools and Documentation Practice Question
Which document formally authorizes a project and assigns the project manager?
⚠ Common exam trap
The trap is confusing the project charter with other project documents like the project management plan or stakeholder register, which serve different purposes and are not the formal authorization.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter is the document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It is typically issued by the project sponsor or initiator and includes high-level information such as project purpose, objectives, and success criteria. It also names the project manager and outlines their responsibilities.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stakeholder register
Why it's wrong here
A stakeholder register records who is affected by or interested in the project, and carries no authorisation or appointment authority. It is tempting because it is a formal project document naming people, but the project charter is the artefact that authorises the project and names the project manager.
- ✗
RACI matrix
Why it's wrong here
A RACI matrix maps responsibility, accountability, consultation and information duties for activities; it neither authorises the project nor appoints the manager. It is tempting because it assigns named accountability, but the project charter is what formally authorises the work and designates the project manager.
- ✗
Project management plan
Why it's wrong here
The project management plan describes how the project will be executed, monitored and controlled; it does not authorise the project or name the project manager. It is tempting because it is the master planning document produced during the project, but the project charter is the artefact that formally authorises the work and assigns the manager.
- ✓
Project charter
Why this is correct
The project charter formally authorises the project and names the project manager, granting authority to commit organisational resources. It satisfies both constraints in the stem, unlike the project management plan, which documents execution approach after authorisation has already been granted.
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official CompTIA exam blueprint
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.