Question 175 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit the change request to the change control board for review. This is correct because the formal change control process dictates that any modification impacting the project baseline—such as scope, cost, or schedule—must be escalated to the Change Control Board (CCB) for governance. The project manager’s role is to assess the impact and then follow the established procedure, not to approve or reject changes unilaterally. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the change control process when a stakeholder requests a scope change; a common trap is choosing to implement the change immediately or negotiate with the stakeholder, but the first action is always to submit the request to the CCB. Remember the mnemonic “S.C.O.P.E.”—Submit, Check impact, Obtain approval, Proceed, Evaluate—to keep the sequence straight.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a key stakeholder requests a change that will affect the project scope. The project manager assesses the impact and finds it will increase costs by 15% and delay the schedule by two weeks. What is the FIRST action the project manager should take?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the change request to the change control board for review.

In project management, when a change request impacts scope, cost, or schedule, the project manager must follow the formal change control process. The first action is to submit the change request to the change control board (CCB) for review and approval, as the project manager does not have unilateral authority to approve or reject changes that affect the project baseline. This ensures proper governance and stakeholder alignment.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reject the change because it will impact schedule and cost.

    Why it's wrong here

    Rejection without analysis may be premature; change control process should be followed.

  • Approve the change since the impact is minimal.

    Why it's wrong here

    The project manager may need change control board approval for scope changes.

  • Submit the change request to the change control board for review.

    Why this is correct

    Proper change control requires formal submission and review.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Implement the change immediately to satisfy the stakeholder.

    Why it's wrong here

    Implementing without following change control process is incorrect.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the misconception that the project manager can approve or reject changes based on personal judgment, when in fact the formal change control process mandates CCB involvement for any change affecting the project baseline.

Detailed technical explanation

How to think about this question

The change control process is defined in the project management plan and typically requires a change request form, impact analysis, and CCB review. The CCB, which includes key stakeholders and sponsors, evaluates trade-offs and approves or denies changes based on business value and risk. In real-world scenarios, skipping this step can lead to budget overruns, schedule delays, and scope creep that undermine project success.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit the change request to the change control board for review. — In project management, when a change request impacts scope, cost, or schedule, the project manager must follow the formal change control process. The first action is to submit the change request to the change control board (CCB) for review and approval, as the project manager does not have unilateral authority to approve or reject changes that affect the project baseline. This ensures proper governance and stakeholder alignment.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?

easy
  • A.Monitor and Control Project Work
  • B.Close Project or Phase
  • C.Direct and Manage Project Work
  • D.Perform Integrated Change Control

Why D: Perform Integrated Change Control (D) is the correct process because it is the formal process within project management that ensures all change requests are reviewed, evaluated for impact on scope, schedule, cost, and quality, and approved or rejected before implementation. This process integrates the change across all knowledge areas and requires documented approval, which directly addresses the project manager's need to evaluate and approve changes before they are implemented.

Variation 2. During project execution, a key stakeholder requests a change that would require additional funding. The project manager should:

medium
  • A.Ask the sponsor for approval
  • B.Submit the change request to the change control board
  • C.Refuse the change because it increases cost
  • D.Implement the change immediately

Why B: In project management, any change that impacts the budget must follow the formal change control process. The project manager should submit the change request to the change control board (CCB) for evaluation and approval, as the CCB has the authority to approve or reject changes that affect cost, scope, or schedule. This ensures that all impacts are assessed and that the project remains aligned with its baseline.

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.