Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project sponsor asks for a document that…

A project sponsor asks for a document that outlines the high-level scope, objectives, and key stakeholders of a new project. Which document should the project manager provide?

⚠ Common exam trap

Many exam-takers confuse the project charter with the scope statement, but the scope statement is a detailed planning document created after the charter, while the charter is the high-level authorization document requested by the sponsor.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter is the correct document because it formally authorizes the project, defines the high-level scope, objectives, and key stakeholders, and is issued by the project sponsor. It serves as the foundational agreement between the sponsor and the project manager, aligning with PMI's PMBOK Guide for initiating a project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope statement

    Why it's wrong here

    The scope statement provides detailed scope, not high-level summary.

  • Project charter

    Why this is correct

    The project charter is the formal authorization document with high-level information.

  • Project management plan

    Why it's wrong here

    The PM plan is comprehensive and detailed, not a high-level overview.

  • Work breakdown structure

    Why it's wrong here

    WBS decomposes scope into deliverables, not high-level objectives.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project sponsor asks for a document that formally authorizes the project and provides the project manager with authority to apply resources. Which document should the project manager provide?

hard
  • A.Project management plan
  • B.Project charter
  • C.Business case
  • D.Scope statement

Why B: (Project charter) is correct because the project charter is the document that formally authorizes the project, provides the project manager with authority to apply organizational resources, and documents initial requirements and high-level scope. Option A (Project management plan) is developed after the charter is approved and describes how the project will be executed, monitored, and controlled. Option C (Business case) justifies the project from a business perspective and is often created before the charter. Option D (Scope statement) defines the project scope, deliverables, and acceptance criteria but does not authorize the project.

Variation 2. Which document formally authorizes the project and assigns the project manager?

easy
  • A.Project management plan
  • B.Scope statement
  • C.Business case
  • D.Project charter

Why D: The project charter is the formal document that authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It is issued by the project sponsor or initiator and formally assigns the project manager, establishing their role and responsibilities from the outset.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.