Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Under budget and behind schedule

CPI > 1 means under budget, SPI < 1 means behind schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Over budget and behind schedule

    Why it's wrong here

    CPI>1 means under budget.

  • Over budget and ahead of schedule

    Why it's wrong here

    CPI >1 is under budget, not over.

  • Under budget and behind schedule

    Why this is correct

    CPI=1.2 indicates under budget; SPI=0.8 indicates behind schedule.

  • Under budget and ahead of schedule

    Why it's wrong here

    SPI<1 means behind schedule.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.