mediumMultiple Choice

PK0-005 Practice Question: A project team is executing the project plan when…

A project team is executing the project plan when a key stakeholder requests a significant change to the scope. The change control board has approved the change. What should the project manager update next?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project management plan and scope baseline

After a change is approved by the change control board, the project manager must update the project management plan and the scope baseline to reflect the new scope.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project management plan and scope baseline

    Why this is correct

    Once the change control board approves a scope change, the approved change must be reflected in the project management plan and its scope baseline, since those documents formally define approved scope, schedule and cost against which performance is measured.

  • ✗

    Risk register

    Why it's wrong here

    The risk register tracks uncertain future events and their responses, not approved scope baselines, so it does not record the change itself. It is updated when the change alters identified risks, for instance introducing new threats requiring response owners.

  • ✗

    Communications plan

    Why it's wrong here

    The communications plan defines who receives project information and how; it does not hold scope, schedule or cost baselines. It is revised when the change alters stakeholder information needs or reporting cadence, not as the primary record of an approved scope change.

  • ✗

    Issue log

    Why it's wrong here

    The issue log records problems currently affecting the project, whereas an approved scope change is a planned baseline revision, not an unresolved issue. It is updated when the change creates a live problem needing resolution, such as a defect or blocker.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.