mediumMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project team is executing the project plan when…
A project team is executing the project plan when a key stakeholder requests a significant change to the scope. The change control board has approved the change. What should the project manager update next?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project management plan and scope baseline
After a change is approved by the change control board, the project manager must update the project management plan and the scope baseline to reflect the new scope.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project management plan and scope baseline
Why this is correct
Upon approval, the project management plan and the scope baseline must be updated to incorporate the change.
- ✗
Risk register
Why it's wrong here
The risk register may be updated if the change introduces new risks, but the immediate priority is to update the project management plan and scope baseline.
- ✗
Communications plan
Why it's wrong here
While communications may need updating, the primary action is to update the project management plan to reflect the approved change.
- ✗
Issue log
Why it's wrong here
The issue log tracks issues, not changes. The change should be reflected in the project management plan.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.