Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is closing a phase of a multi-phase program. The phase deliverables have been accepted by the customer, but several team members will continue into the next phase. Which activity should the project manager perform as part of closing this phase?

⚠ Common exam trap

The trap here is applying full project closure activities, such as releasing all resources, to a phase that is merely one step in an ongoing program.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Confirm that the phase deliverables were accepted and archive the phase records for future reference.

Closing a phase within a program involves verifying that the phase deliverables were accepted, documenting that acceptance, archiving phase records, and capturing lessons learned. Because the project continues, resources remain assigned and no new charter or automatic re-baselining occurs. This preserves continuity and organizational knowledge while formally acknowledging phase completion.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Confirm that the phase deliverables were accepted and archive the phase records for future reference.

    Why this is correct

    Phase closure verifies that the phase's deliverables met acceptance criteria and that the phase objective was achieved before the next phase begins. Documenting that acceptance, archiving phase records, and capturing lessons learned preserves organizational knowledge and provides the transition basis for the following phase, while leaving ongoing resources in place for continued work.

  • ✗

    Initiate a new project charter for the next phase so the team has formal authorization to continue.

    Why it's wrong here

    A multi-phase program is governed by a single project charter that authorizes the overall project; individual phases do not require new charters. Creating a separate charter for the next phase would incorrectly fragment authority and duplicate governance. Phase transitions are handled through phase gate reviews and updated plans, not through re-chartering the work.

  • ✗

    Re-baseline the schedule and cost baselines to reflect the completed phase before starting the next one.

    Why it's wrong here

    Re-baselining is a formal change that resets approved baselines and is typically reserved for significant, approved scope changes, not routine phase completion. Phase closure does not automatically authorize new baselines. Any baseline change would require a change request and approval through integrated change control, and routine phase transitions generally proceed against the existing approved baselines.

  • ✗

    Release all project resources and finalize the project's administrative closure records.

    Why it's wrong here

    Releasing all resources and finalizing administrative closure applies to closing the entire project, not a single phase within a program. Since team members continue into the next phase, releasing them would disrupt continuity. Phase closure focuses on confirming that phase deliverables were accepted and transitioning work forward, while full resource release occurs only when the whole project ends.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.