A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Delaying a critical path activity delays the project.
The critical path has the longest duration and zero float. Any delay on the critical path delays the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Delaying a critical path activity delays the project.
Why this is correct
Any delay on critical path delays project.
- ✗
Critical path activities can have negative float.
Why it's wrong here
Negative float indicates a schedule issue, but normally critical path has zero float.
- ✗
Activities on the critical path have positive float.
Why it's wrong here
Critical path activities have zero float.
- ✗
There can be only one critical path.
Why it's wrong here
Multiple critical paths can exist.
- ✓
It has the longest duration in the project.
Why this is correct
Critical path is the longest path.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.