PK0-005 Tools and Documentation Practice Question
A project team is using Jira for agile development. They have a list of features to be developed over multiple sprints. What is the term for this list, which represents all the work planned for the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Product backlog
In agile, the product backlog is a prioritized list of all desired work for the project. Sprint backlog is for a single sprint.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Product backlog
Why this is correct
Correct. The product backlog is the master list of all work.
- ✗
Kanban board
Why it's wrong here
A Kanban board visualizes work in progress, not the entire backlog.
- ✗
Sprint backlog
Why it's wrong here
The sprint backlog contains work for one sprint, not the entire project.
- ✗
Burnup chart
Why it's wrong here
A burnup chart tracks completed work over time, not a list of work.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.