PK0-005 Tools and Documentation Practice Question
A project team is using Jira for agile development. They have a list of features to be developed over multiple sprints. What is the term for this list, which represents all the work planned for the project?
⚠ Common exam trap
PK0-005 often tests the distinction between product backlog (all planned work) and sprint backlog (work for one sprint), and candidates may incorrectly choose sprint backlog if they overlook the phrase 'over multiple sprints'.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Product backlog
The product backlog is the comprehensive list of all features, requirements, and work planned for the project, maintained by the product owner. It represents the single source of requirements for any changes to the product. In agile development, the product backlog is refined and prioritized over time.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Product backlog
Why this is correct
The product backlog is the single ordered list of all features, requirements and work planned for the project, from which sprint backlogs are drawn. It matches the description of features to be developed across multiple sprints.
- ✗
Kanban board
Why it's wrong here
A Kanban board visualises workflow stages and limits work in progress; it does not hold the full ordered list of planned features. That list is the product backlog. Kanban would be correct where the question asks how continuous flow of in-progress work is displayed and constrained.
- ✗
Sprint backlog
Why it's wrong here
A sprint backlog contains only the items selected for the current sprint, not all work planned across multiple sprints. The full ordered list is the product backlog. Sprint backlog would be correct where the question asks what the team commits to during one iteration.
- ✗
Burnup chart
Why it's wrong here
A burnup chart tracks completed work against total scope over time; it is a progress visualisation, not a list of features. The full planned work list is the product backlog. Burnup would be correct where the question asks how remaining scope and completion trend are charted.
Go deeper
Related to this question
About these practice questions
One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official CompTIA exam blueprint
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.