PK0-005 Project Management Concepts Practice Question
A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Predictive
Predictive (waterfall) is best for projects with stable, well-understood requirements. Agile is for evolving requirements, and hybrid combines both. Scrum is an agile framework.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Hybrid
Why it's wrong here
Hybrid combines elements and is not necessary when requirements are stable.
- ✗
Scrum
Why it's wrong here
Scrum is an agile framework.
- ✗
Agile
Why it's wrong here
Agile is for evolving requirements.
- ✓
Predictive
Why this is correct
Predictive (waterfall) works well with fixed scope and stable requirements.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.