Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Predictive

Predictive (waterfall) is best for projects with stable, well-understood requirements. Agile is for evolving requirements, and hybrid combines both. Scrum is an agile framework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Hybrid

    Why it's wrong here

    Hybrid combines elements and is not necessary when requirements are stable.

  • Scrum

    Why it's wrong here

    Scrum is an agile framework.

  • Agile

    Why it's wrong here

    Agile is for evolving requirements.

  • Predictive

    Why this is correct

    Predictive (waterfall) works well with fixed scope and stable requirements.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.