Courseiva

PK0-005 · topic practice

Basics of IT Infrastructure and IT Project Management practice questions

This domain covers the IT infrastructure knowledge a project manager needs plus foundational project management mechanics. Expect ordering questions on WBS and schedule creation, plus scenario items on switch selection, data center design, high availability, latency, and other infrastructure components evaluated against stated business and technical requirements.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Basics of IT Infrastructure and IT Project Management

What the exam tests

What to know about Basics of IT Infrastructure and IT Project Management

Be able to sequence WBS and schedule steps correctly and map infrastructure components to stated requirements like high availability and low latency. The single most important thing: match each technical choice to the explicit requirement in the scenario, not to general best practice.

Ordering WBS steps: scope statement, deliverables, decomposition, work packages, WBS dictionary

Ordering schedule steps: define activities, sequence, estimate durations, develop schedule, baseline

Switch selection factors: port count, PoE, throughput, VLAN support, managed vs unmanaged, cost

Data center components: redundant power, cooling, UPS, RAID, load balancing, low-latency networking

Watch out for

Common Basics of IT Infrastructure and IT Project Management exam traps

  • ▸Confusing WBS creation order with schedule creation order, or placing estimation before activity sequencing and decomposition
  • ▸Choosing switches on brand or price alone while ignoring required port count, PoE, throughput, or manageability
  • ▸Treating high availability as a single component instead of combining redundancy, failover, and low-latency networking

Practice set

Basics of IT Infrastructure and IT Project Management questions

20 questions · select your answer, then reveal the explanation

A project manager is deploying a new web application to a cloud environment. The application requires high availability and automatic scaling based on traffic. Which IT infrastructure component should the project manager use to meet these requirements?

During a database migration project, the team encounters an error when trying to connect to the new database server from the application server. The network team confirms that the ports are open and the firewall rules are correct. The database team reports that the database service is running and listening on the expected port. Which of the following is the MOST likely cause of the connectivity issue?

Which TWO of the following are key considerations when designing an IT infrastructure for a new data center?

A project manager is planning the deployment of a new web application. The IT team has identified the following requirements: the application must be accessible 24/7, handle traffic spikes, and maintain session persistence. Which TWO infrastructure components should the project manager include in the design to meet these requirements?

A project manager is working on a project where a new team member is not receiving project updates. The team member reports that they can access the project portal but not the project emails. Based on the exhibit, what is the most likely cause?

Exhibit

Refer to the exhibit.

Command: ping -c 4 10.0.1.15
Output:
PING 10.0.1.15 (10.0.1.15) 56(84) bytes of data.
From 10.0.1.1 icmp_seq=1 Destination Host Unreachable
From 10.0.1.1 icmp_seq=2 Destination Host Unreachable
From 10.0.1.1 icmp_seq=3 Destination Host Unreachable
From 10.0.1.1 icmp_seq=4 Destination Host Unreachable

--- 10.0.1.15 ping statistics ---
4 packets transmitted, 0 received, +4 errors, 100% packet loss, time 3005ms

Command: arp -a
Output:
? (10.0.1.1) at 00:1a:2b:3c:4d:5e [ether] on eth0
? (10.0.1.15) at <incomplete> on eth0

Arrange the steps for performing procurement management.

Drag or tap steps into the slots.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Match each project management knowledge area to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensuring the project includes all required work

Managing timely completion of the project

Planning, estimating, budgeting, and controlling costs

Ensuring the project meets its intended objectives

Identifying, analyzing, and responding to project risks

A company is implementing a hybrid cloud solution to meet fluctuating demand. The project budget is fixed, and the timeline is aggressive. Which project management approach is most appropriate to manage scope changes while controlling costs?

A network engineer configures a switch port as shown. After implementation, the connected server is experiencing intermittent network drops. Which configuration change should the project team recommend to resolve the issue?

Exhibit

Refer to the exhibit.

Exhibit:
```
interface GigabitEthernet0/1
 switchport mode trunk
 switchport trunk allowed vlan 10,20,30
 spanning-tree portfast
```

A cloud engineer created the access control policy shown. The project requires that only the development team (IP range 10.0.0.0/16) can upload backup files to the backup storage location 'project-backup'. However, the policy is not working as expected. What is the most likely cause?

Exhibit

Refer to the exhibit.

Exhibit:
```
{
  "Version": "2012-10-17",
  "Statement": [
    {
      "Effect": "Allow",
      "Action": "s3:PutObject",
      "Resource": "arn:aws:s3:::project-backup/*",
      "Condition": {
        "IpAddress": {
          "aws:SourceIp": "10.0.0.0/16"
        }
      }
    }
  ]
}
```
Question 11easymultiple choice
Review the full subnetting walkthrough →

A project team is deploying a new application, and the error log shows repeated connection refused errors. The database server is on a separate subnet. What is the most likely cause of this issue?

Exhibit

Refer to the exhibit.

Exhibit:
```
2023-09-15 14:23:45 ERROR [main] com.example.app.DatabaseConnection - Connection refused: connect
2023-09-15 14:23:46 WARN  [main] com.example.app.DatabaseConnection - Retrying connection...
2023-09-15 14:23:50 ERROR [main] com.example.app.DatabaseConnection - Connection refused: connect
2023-09-15 14:23:51 FATAL [main] com.example.app.Application - Unable to start application due to database failure
```

Which TWO of the following are common causes of project delays in IT infrastructure projects? (Choose two.)

Question 13easymultiple choice
Study the full virtualization explanation →

A project to consolidate multiple physical servers into a private cloud. What is the primary benefit of using server virtualization?

While upgrading storage, the project team discovers that the SAN switch is saturated. What immediate step should the project manager take?

A project involves installing new firewalls across multiple sites. The project manager notices the schedule is slipping due to site-specific electrical requirements that were not initially identified. What is the best course of action?

A team is implementing a disaster recovery plan that includes replication to a secondary data center. Which metric should the project manager prioritize defining in the DR plan?

During a server migration project, the team discovers that the new hardware requires a specific firmware version not currently installed. The project schedule is tight. What is the best course of action?

A data center upgrade project requires redundancy for critical systems. Which three components should be redundant? (Choose three.)

Question 19hardmultiple choice
Review the full routing breakdown →

A project involves upgrading the network core switches to support higher throughput and new routing protocols. The project manager schedules a cutover during a weekend maintenance window. On Friday evening, the team discovers that the new switches do not have the correct software license for the advanced routing protocols required per the architecture. The current old switches are still functional. The project manager must decide the best course of action.

A project manager is planning the network cutover for a new branch office. The project charter requires that the branch remain reachable even if its primary WAN circuit fails, and that the failover be validated before go-live. Which TWO activities should the project manager include in the cutover plan? (Choose two.)

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Basics of IT Infrastructure and IT Project Management sessions

Start a Basics of IT Infrastructure and IT Project Management only practice session

Every question in these sessions is drawn from the Basics of IT Infrastructure and IT Project Management domain — nothing else.

Related practice questions

Related PK0-005 topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PK0-005 exam test about Basics of IT Infrastructure and IT Project Management?
Be able to sequence WBS and schedule steps correctly and map infrastructure components to stated requirements like high availability and low latency. The single most important thing: match each technical choice to the explicit requirement in the scenario, not to general best practice.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Basics of IT Infrastructure and IT Project Management questions in a focused session?
Yes — the session launcher on this page draws every question from the Basics of IT Infrastructure and IT Project Management domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PK0-005 topics?
Use the topic links above to move to related areas, or go back to the PK0-005 question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the PK0-005 exam covers. They are not copied from any real exam or dump site.