Courseiva

PK0-005 · topic practice

Basics of IT Infrastructure and IT Project Management practice questions

Practise CompTIA Project+ PK0-005 Basics of IT Infrastructure and IT Project Management practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Reviewed byJohnson Ajibi· MSc IT Security
20 questionsDomain: Basics of IT Infrastructure and IT Project Management

What the exam tests

What to know about Basics of IT Infrastructure and IT Project Management

Basics of IT Infrastructure and IT Project Management questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Basics of IT Infrastructure and IT Project Management exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Practice set

Basics of IT Infrastructure and IT Project Management questions

20 questions · select your answer, then reveal the explanation

A project manager is working on a project where a new team member is not receiving project updates. The team member reports that they can access the project portal but not the project emails. Based on the exhibit, what is the most likely cause?

Exhibit

Refer to the exhibit.

Command: ping -c 4 10.0.1.15
Output:
PING 10.0.1.15 (10.0.1.15) 56(84) bytes of data.
From 10.0.1.1 icmp_seq=1 Destination Host Unreachable
From 10.0.1.1 icmp_seq=2 Destination Host Unreachable
From 10.0.1.1 icmp_seq=3 Destination Host Unreachable
From 10.0.1.1 icmp_seq=4 Destination Host Unreachable

--- 10.0.1.15 ping statistics ---
4 packets transmitted, 0 received, +4 errors, 100% packet loss, time 3005ms

Command: arp -a
Output:
? (10.0.1.1) at 00:1a:2b:3c:4d:5e [ether] on eth0
? (10.0.1.15) at <incomplete> on eth0

An IT project manager is tasked with deploying a new inventory management system. The project requires installing software on 100 workstations and training users. Which factor is most critical to include in the project schedule?

A project to migrate on-premises email to Office 365 is behind schedule. The project sponsor asks the project manager to add more resources to accelerate the timeline. The project manager should first:

A network engineer configures a switch port as shown. After implementation, the connected server is experiencing intermittent network drops. Which configuration change should the project team recommend to resolve the issue?

Exhibit

Refer to the exhibit.

Exhibit:
```
interface GigabitEthernet0/1
 switchport mode trunk
 switchport trunk allowed vlan 10,20,30
 spanning-tree portfast
```

A cloud engineer created the access control policy shown. The project requires that only the development team (IP range 10.0.0.0/16) can upload backup files to the backup storage location 'project-backup'. However, the policy is not working as expected. What is the most likely cause?

Exhibit

Refer to the exhibit.

Exhibit:
```
{
  "Version": "2012-10-17",
  "Statement": [
    {
      "Effect": "Allow",
      "Action": "s3:PutObject",
      "Resource": "arn:aws:s3:::project-backup/*",
      "Condition": {
        "IpAddress": {
          "aws:SourceIp": "10.0.0.0/16"
        }
      }
    }
  ]
}
```
Question 6hardmultiple choice
Review the full routing breakdown →

A project involves upgrading the network core switches to support higher throughput and new routing protocols. The project manager schedules a cutover during a weekend maintenance window. On Friday evening, the team discovers that the new switches do not have the correct software license for the advanced routing protocols required per the architecture. The current old switches are still functional. The project manager must decide the best course of action.

Refer to the exhibit. A project manager is reviewing the security configuration of a project's cloud storage. Which of the following is the MOST significant security risk?

Exhibit

{
  "Version": "2012-10-17",
  "Statement": [
    {
      "Effect": "Allow",
      "Action": "s3:GetObject",
      "Resource": "arn:aws:s3:::example-bucket/*",
      "Principal": "*"
    }
  ]
}

A project manager is deploying a new web application to a cloud environment. The application requires high availability and automatic scaling based on traffic. Which IT infrastructure component should the project manager use to meet these requirements?

During a database migration project, the team encounters an error when trying to connect to the new database server from the application server. The network team confirms that the ports are open and the firewall rules are correct. The database team reports that the database service is running and listening on the expected port. Which of the following is the MOST likely cause of the connectivity issue?

A project manager is overseeing the implementation of a new customer relationship management (CRM) system. The vendor requires access to the company's internal network to install and configure the software. Which of the following is the BEST practice to ensure security while allowing vendor access?

Which TWO of the following are key considerations when designing an IT infrastructure for a new data center?

A project manager is leading a project to upgrade the storage area network (SAN) for a hospital's electronic health records (EHR) system. The current SAN is reaching capacity and has performance issues during peak hours. The new SAN must support high availability with synchronous replication between two data centers located 10 km apart. The project budget is tight, and the timeline is aggressive. During a risk assessment, the project manager identifies that the fiber optic cable between the data centers is owned by a third-party provider and has a history of outages. The project sponsor is concerned about meeting the go-live date and asks the project manager to recommend a course of action to mitigate the risk of cable outages affecting the SAN replication. Which of the following is the BEST course of action?

A project manager is planning the deployment of a new web application. The IT team has identified the following requirements: the application must be accessible 24/7, handle traffic spikes, and maintain session persistence. Which TWO infrastructure components should the project manager include in the design to meet these requirements?

Question 14easymultiple choice
Read the full VPN explanation →

You are the project manager for a mid-sized company that provides an online customer portal. The portal is hosted on a single virtual machine (VM) in the company's on-premises data center with 4 vCPUs, 16 GB RAM, and a 500 GB HDD. The VM runs Windows Server 2019 and hosts both the web server (IIS) and the database (SQL Server Express). Users have been reporting slow performance, especially during peak hours (10 AM - 2 PM). The system administrator notes that CPU usage spikes to 95% during those times, and disk I/O latency averages 50 ms. The company's budget is limited, and they want a cost-effective solution that can be implemented within two weeks. The project sponsor suggests migrating to the cloud, but the IT director is concerned about security and compliance. The company has no existing cloud infrastructure or virtual private network (VPN) to the cloud. You need to propose a solution that improves performance without incurring high costs or long delays. Which of the following is the BEST course of action?

Put the steps for creating a work breakdown structure (WBS) in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Order the steps for creating a project schedule.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Arrange the steps for performing procurement management.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Match each project management knowledge area to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensuring the project includes all required work

Managing timely completion of the project

Planning, estimating, budgeting, and controlling costs

Ensuring the project meets its intended objectives

Identifying, analyzing, and responding to project risks

Match each acronym to its definition in project management.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Statement of Work

Work Breakdown Structure

Request for Proposal

Return on Investment

Key Performance Indicator

Match each procurement document to its purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Solicit general information about vendor capabilities

Request detailed proposals for a specific project need

Request pricing for specific goods or services

Request competitive bids for clearly defined work

Formal document to authorize a purchase transaction

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Basics of IT Infrastructure and IT Project Management sessions

Start a Basics of IT Infrastructure and IT Project Management only practice session

Every question in these sessions is drawn from the Basics of IT Infrastructure and IT Project Management domain — nothing else.

Related practice questions

Related PK0-005 topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PK0-005 exam test about Basics of IT Infrastructure and IT Project Management?
Basics of IT Infrastructure and IT Project Management questions test whether you can apply the concept in context, not just recognise a definition.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Basics of IT Infrastructure and IT Project Management questions in a focused session?
Yes — the session launcher on this page draws every question from the Basics of IT Infrastructure and IT Project Management domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PK0-005 topics?
Use the topic links above to move to related areas, or go back to the PK0-005 question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the PK0-005 exam covers. They are not copied from any real exam or dump site.