PK0-005 Practice Question: During project planning, the team identifies that…

During project planning, the team identifies that a key developer is only available 50% of the time. This is an example of which type of constraint?

⚠ Common exam trap

PK0-005 often tests the confusion between resource constraints and schedule constraints, as limited availability can impact the schedule, but the root cause is resource availability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Resource constraint

A resource constraint refers to limitations on the availability of resources, such as personnel, equipment, or materials. The key developer being available only 50% of the time is a classic example of a resource constraint because it restricts how much work can be assigned to that person.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Technical constraint

    Why it's wrong here

    Availability of a person is a resource constraint, not a technical one; technical constraints concern solution architecture, tools or standards. It tempts because the developer's skill is technical, but the limiting factor here is their time, which belongs in resource planning.

  • ✓

    Resource constraint

    Why this is correct

    A key developer available only half the time limits the amount of labour the project can apply, which is a resource constraint. Resource constraints concern the availability, quantity or capability of people, equipment or materials, distinct from time, cost or scope limitations.

  • ✗

    Schedule constraint

    Why it's wrong here

    Schedule constraints govern the project timeline and deadlines, not the quantity of a resource's available working time. A developer available only 50% is a resource constraint; schedule would apply if the completion date itself were fixed or compressed.

  • ✗

    Cost constraint

    Why it's wrong here

    Cost constraint concerns the approved budget and funding limits for the project. A developer's 50% availability restricts time, not money, so it maps to the schedule constraint; cost would apply if the budget for that resource were capped.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.