Courseiva
Tools and DocumentationmediumMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

During a sprint review, the product owner notices that the team completed 30 story points in the previous sprint and 25 in the current sprint. The project manager wants to track the average story points completed per sprint to predict future performance. Which metric should be used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Velocity

Velocity is the average story points completed per sprint, used for forecasting.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Burnup chart

    Why it's wrong here

    Burnup chart shows completed work over time, not average per sprint.

  • Burndown chart

    Why it's wrong here

    Burndown chart shows remaining work over time, not average completion rate.

  • Velocity

    Why this is correct

    Velocity measures story points completed per sprint, averaged for forecasting.

  • Planned value

    Why it's wrong here

    Planned value is an EVM term, not used for sprint performance.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.