PK0-005 Tools and Documentation Practice Question
During a sprint review, the product owner notices that the team completed 30 story points in the previous sprint and 25 in the current sprint. The project manager wants to track the average story points completed per sprint to predict future performance. Which metric should be used?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Velocity
Velocity is the average story points completed per sprint, used for forecasting.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Burnup chart
Why it's wrong here
Burnup chart shows completed work over time, not average per sprint.
- ✗
Burndown chart
Why it's wrong here
Burndown chart shows remaining work over time, not average completion rate.
- ✓
Velocity
Why this is correct
Velocity measures story points completed per sprint, averaged for forecasting.
- ✗
Planned value
Why it's wrong here
Planned value is an EVM term, not used for sprint performance.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.