Courseiva
Project Life CyclehardMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project closure, which three activities should be performed? (Select THREE)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Obtain formal acceptance

Closure activities include lessons learned, obtaining formal acceptance, and archiving project documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Obtain formal acceptance

    Why this is correct

    Formal sign-off is required for closure.

  • Conduct lessons learned

    Why this is correct

    Capturing lessons learned is a key closing activity.

  • Develop project charter

    Why it's wrong here

    Charter is created during initiation.

  • Archive project documents

    Why this is correct

    Archiving ensures records are stored.

  • Create risk register

    Why it's wrong here

    Risk register is created during planning.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.