hardMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project manager is developing the risk…
A project manager is developing the risk management plan. Which of the following is the primary purpose of this plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Define how risk management activities will be conducted
The risk management plan describes how risk management will be performed, while the risk register captures the actual risks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Define how risk management activities will be conducted
Why this is correct
The risk management plan outlines the methodology, roles, budgeting, and timing for risk management.
- ✗
List all identified risks
Why it's wrong here
Identified risks are documented in the risk register, not the risk management plan.
- ✗
Prioritize risks
Why it's wrong here
Risk prioritization occurs during risk analysis and is recorded in the risk register.
- ✗
Assign risk owners
Why it's wrong here
Risk owners are assigned in the risk register as part of risk response planning.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.