PK0-005 Tools and Documentation Practice Question
Which THREE items are typically found in a project management plan? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule management plan
The project management plan contains subsidiary plans, including scope, schedule, cost, quality, etc. The project charter and WBS are separate documents.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule management plan
Why this is correct
Schedule management plan is a subsidiary plan.
- ✓
Scope management plan
Why this is correct
Scope management plan is a subsidiary plan.
- ✗
Project charter
Why it's wrong here
The charter is an input to the planning process, not part of the plan.
- ✗
Work breakdown structure (WBS)
Why it's wrong here
WBS is a scope baseline component, not a plan.
- ✓
Risk management plan
Why this is correct
Risk management plan is a subsidiary plan.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.