Which THREE items are typically found in a project management plan? (Select THREE).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule management plan

The project management plan contains subsidiary plans, including scope, schedule, cost, quality, etc. The project charter and WBS are separate documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule management plan

    Why this is correct

    Schedule management plan is a subsidiary plan.

  • Scope management plan

    Why this is correct

    Scope management plan is a subsidiary plan.

  • Project charter

    Why it's wrong here

    The charter is an input to the planning process, not part of the plan.

  • Work breakdown structure (WBS)

    Why it's wrong here

    WBS is a scope baseline component, not a plan.

  • Risk management plan

    Why this is correct

    Risk management plan is a subsidiary plan.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.