PK0-005 Tools and Documentation Practice Question
A project manager is selecting two documents that are essential for defining project scope. Which TWO documents should they choose?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Work breakdown structure (WBS)
The WBS breaks down the work into manageable components, and the scope statement defines the project scope, deliverables, and boundaries. The risk register lists risks, the communication plan defines communication, and the RACI matrix assigns responsibilities.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Communication plan
Why it's wrong here
The communication plan outlines communication, not scope.
- ✗
Risk register
Why it's wrong here
The risk register lists risks, not scope definition.
- ✓
Work breakdown structure (WBS)
Why this is correct
The WBS decomposes the project scope into work packages.
- ✓
Scope statement
Why this is correct
The scope statement formally defines the project scope.
- ✗
RACI matrix
Why it's wrong here
The RACI matrix shows responsibilities, not scope.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.