Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

0 days

This is a simple linear network: A (5) -> B (7) -> C (4). The critical path is A-B-C = 5+7+4=16 days. Activity B is on the critical path (no other paths), so its total float is zero. Total float for any activity on the critical path is zero.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 5 days

    Why it's wrong here

    This is the duration of Activity A, not the float for B.

  • 7 days

    Why it's wrong here

    This is the duration of Activity B, not its float.

  • 4 days

    Why it's wrong here

    This is the duration of Activity C, not the float for B.

  • 0 days

    Why this is correct

    Correct. Activity B is on the critical path, so its total float is 0 days.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.