Courseiva
Tools and DocumentationmediumMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project has a BAC of $200,000. After three months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. What is the cost variance (CV) and what does it indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

CV = -$10,000; the project is over budget

CV = EV - AC = $80,000 - $90,000 = -$10,000. Negative CV means over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • CV = -$10,000; the project is over budget

    Why this is correct

    Correct calculation and interpretation.

  • CV = $10,000; the project is ahead of schedule

    Why it's wrong here

    Incorrect sign and interpretation.

  • CV = $10,000; the project is under budget

    Why it's wrong here

    Incorrect sign; AC > EV.

  • CV = -$10,000; the project is behind schedule

    Why it's wrong here

    CV is cost, not schedule.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.