Courseiva
Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project has a BAC of $200,000. After three months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. What is the cost variance (CV) and what does it indicate?

⚠ Common exam trap

PK0-005 often tests the confusion between Cost Variance and Schedule Variance — candidates see a negative number and reflexively pick 'behind schedule' (Option D) instead of recognizing that CV specifically measures budget performance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

CV = -$10,000; the project is over budget

Cost Variance is calculated as CV = EV − AC. Here EV = $80,000 and AC = $90,000, so CV = $80,000 − $90,000 = −$10,000. A negative CV means the project has spent more than the value of work completed, i.e., it is over budget. Option A states both the correct value and the correct interpretation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    CV = -$10,000; the project is over budget

    Why this is correct

    Cost variance is calculated as EV minus AC, giving $80,000 − $90,000 = −$10,000. A negative CV means the project has spent more than the value earned to date, so it is over budget. This directly satisfies the stem's figures and correctly interprets the shortfall.

  • ✗

    CV = $10,000; the project is ahead of schedule

    Why it's wrong here

    CV is EV minus AC, giving -$10,000, not $10,000; a negative figure signals overspending, and schedule status comes from SV, not CV. The $10,000 magnitude is tempting because it matches the EV/AC gap, but the sign is inverted and the interpretation belongs to a different metric.

  • ✗

    CV = $10,000; the project is under budget

    Why it's wrong here

    CV equals EV minus AC, which is -$10,000 here, so the project is over budget, not under. The $10,000 figure is tempting because it matches the absolute EV/AC difference, but the negative sign is what determines the direction of the variance.

  • ✗

    CV = -$10,000; the project is behind schedule

    Why it's wrong here

    CV is EV minus AC, giving $80,000 - $90,000 = -$10,000, which indicates a cost overrun, not a schedule position; schedule status comes from SV. It is tempting because negative variance sounds like delay, but this formula is the correct choice when asked for schedule variance.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.