PK0-005 Tools and Documentation Practice Question
A project team uses a tool that shows only major events or deadlines, such as the start and end of phases. Which type of chart are they using?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Milestone chart
A milestone chart displays key events (milestones) along a timeline. Gantt charts show all tasks, network diagrams show dependencies, and burndown charts track remaining work over time.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Gantt chart
Why it's wrong here
Gantt charts show all tasks, not just milestones.
- ✗
Network diagram
Why it's wrong here
Network diagrams show task dependencies and the critical path, not just milestones.
- ✗
Burndown chart
Why it's wrong here
Burndown charts track remaining work over a sprint.
- ✓
Milestone chart
Why this is correct
Milestone charts highlight key events or deadlines.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.