PK0-005 Project Management Concepts Practice Question
A project manager is planning a construction project and identifies that the project has a fixed budget and a strict deadline. The sponsor emphasizes that quality cannot be compromised. Which THREE constraints are directly affected when a change request is approved? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule
The triple constraint includes scope, cost, and schedule. Quality is also a constraint but often considered as part of the triple constraint triangle.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule
Why this is correct
Changes can affect the timeline.
- ✗
Resources
Why it's wrong here
Resources are not a primary constraint; they are derived from cost and schedule.
- ✗
Risk
Why it's wrong here
Risk is affected but not a primary constraint in the triple constraint model.
- ✓
Scope
Why this is correct
Changes affect the scope of work.
- ✓
Cost
Why this is correct
Changes impact the budget.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.