PK0-005 Practice Question: In which project life cycle phase are the key…

In which project life cycle phase are the key performance indicators (KPIs) typically established to measure project success?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Planning

Key performance indicators (KPIs) are established during the planning phase as part of the project management plan to define how project success will be measured. Option A is incorrect because the execution phase is where the project work is performed and KPIs are used to monitor progress, but they are not established here. Option C is incorrect because the closure phase involves reviewing KPIs to evaluate project success, not setting them. Option D is incorrect because the initiation phase focuses on project authorization and high-level objectives, not the detailed definition of KPIs.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Execution

    Why it's wrong here

    KPIs are defined during planning, not execution; by the time work begins, measurement baselines should already exist. Execution is where those agreed metrics are tracked and reported against. Choosing it confuses the phase that consumes KPIs with the phase that establishes them, which is the planning phase.

  • ✓

    Planning

    Why this is correct

    KPIs are defined during planning, when scope, objectives and success criteria are agreed. Establishing them here gives the team measurable baselines to track execution and closure against, rather than defining success retrospectively during monitoring or closing.

  • ✗

    Closure

    Why it's wrong here

    KPIs are defined during planning, where objectives, scope and success criteria are agreed before execution begins; closure only verifies them against delivered outcomes. Closure is tempting because final reporting and benefits realisation happen there, so metrics appear to belong to it, but establishing them then leaves no baseline for monitoring.

  • ✗

    Initiation

    Why it's wrong here

    Initiation produces the project charter and stakeholder register; KPIs measuring delivery success are defined later, once scope and baselines exist. Initiation is correct for authorising the project and appointing the sponsor, not for setting performance measures.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.