easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: In which project life cycle phase are the key…
In which project life cycle phase are the key performance indicators (KPIs) typically established to measure project success?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Planning
Key performance indicators (KPIs) are established during the planning phase as part of the project management plan to define how project success will be measured. Option A is incorrect because the execution phase is where the project work is performed and KPIs are used to monitor progress, but they are not established here. Option C is incorrect because the closure phase involves reviewing KPIs to evaluate project success, not setting them. Option D is incorrect because the initiation phase focuses on project authorization and high-level objectives, not the detailed definition of KPIs.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Execution
Why it's wrong here
Uses KPIs.
- ✓
Planning
Why this is correct
KPIs are defined in planning.
- ✗
Closure
Why it's wrong here
Reviews KPIs.
- ✗
Initiation
Why it's wrong here
Authorization phase.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.