easyMultiple ChoiceObjective-mapped
PK0-005 The difference between a risk and an issue? Practice Question
What is the difference between a risk and an issue?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risks are uncertain future events; issues are current problems
A risk is an uncertain future event; an issue is a current problem that has occurred.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risks are uncertain future events; issues are current problems
Why this is correct
Correct distinction.
- ✗
There is no difference
Why it's wrong here
They are distinct concepts.
- ✗
Risks are always negative; issues can be positive
Why it's wrong here
Risks can be positive (opportunities) too.
- ✗
Issues are identified in risk register
Why it's wrong here
Issues are in issue log, not risk register.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.