Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During execution, the project manager receives a…

During execution, the project manager receives a customer change request to add a significant feature. Analysis shows the change will increase the budget by 15% and extend the schedule by two months. What should the project manager do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the change to the change control board

The project manager must submit the change request to the change control board (CCB) for evaluation and approval, as it exceeds typical thresholds. Approving or rejecting without CCB is not allowed; updating the plan occurs only after approval.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approve the change

    Why it's wrong here

    Project managers rarely approve major changes; CCB approval is required.

  • Reject the change

    Why it's wrong here

    The change should be evaluated by the CCB, not unilaterally rejected.

  • Submit the change to the change control board

    Why this is correct

    Formal change control requires CCB review for significant changes.

  • Update the project plan

    Why it's wrong here

    Updating the plan happens after the change is approved.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a project's executing phase, a key team member requests a change to the project scope. What should the project manager do first?

easy
  • A.Submit the change request to the change control board
  • B.Reject the change to avoid scope creep
  • C.Update the project management plan directly
  • D.Approve the change immediately to maintain team morale

Why A: Following the change control process, the first step is to submit a formal change request, which will then be evaluated by the change control board.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.