Question 88 of 500
Project Life Cycle PhaseshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit the change to the change control board (CCB) first. This is correct because the change request significantly exceeds typical project thresholds—a 15% budget increase and a two-month schedule extension—meaning the project manager lacks the authority to approve or reject it independently; the formal change control process requires escalation to the CCB for evaluation and decision. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the change management process during execution, where a common trap is to think the project manager can update the project plan or negotiate directly with the customer before formal approval. Remember the key sequence: receive, document, submit to CCB—never skip to planning or rejection. A helpful memory tip is "CCB First, Plan Later," reinforcing that the board must rule before any implementation steps occur.

PK0-005 Project Life Cycle Phases Practice Question

This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During execution, the project manager receives a customer change request to add a significant feature. Analysis shows the change will increase the budget by 15% and extend the schedule by two months. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the change to the change control board

The project manager must submit the change request to the change control board (CCB) for evaluation and approval, as it exceeds typical thresholds. Approving or rejecting without CCB is not allowed; updating the plan occurs only after approval.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approve the change

    Why it's wrong here

    Project managers rarely approve major changes; CCB approval is required.

  • Reject the change

    Why it's wrong here

    The change should be evaluated by the CCB, not unilaterally rejected.

  • Submit the change to the change control board

    Why this is correct

    Formal change control requires CCB review for significant changes.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Update the project plan

    Why it's wrong here

    Updating the plan happens after the change is approved.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit the change to the change control board — The project manager must submit the change request to the change control board (CCB) for evaluation and approval, as it exceeds typical thresholds. Approving or rejecting without CCB is not allowed; updating the plan occurs only after approval.

What should I do if I get this PK0-005 question wrong?

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a project's executing phase, a key team member requests a change to the project scope. What should the project manager do first?

easy
  • A.Submit the change request to the change control board
  • B.Reject the change to avoid scope creep
  • C.Update the project management plan directly
  • D.Approve the change immediately to maintain team morale

Why A: Following the change control process, the first step is to submit a formal change request, which will then be evaluated by the change control board.

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.