Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analogous estimation

Analogous estimation uses historical data from similar projects, adjusted for differences.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Bottom-up estimation

    Why it's wrong here

    Bottom-up estimates individual work packages and rolls them up.

  • Parametric estimation

    Why it's wrong here

    Parametric uses statistical relationships between variables.

  • Analogous estimation

    Why this is correct

    Analogous uses historical data from similar projects.

  • Three-point estimation

    Why it's wrong here

    Three-point uses optimistic, pessimistic, and most likely estimates.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.