Question 406 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is FS, FS, SS because the three dependency types described map exactly to Finish-to-Start, Finish-to-Start, and Start-to-Start. In project schedule dependency types, a Finish-to-Start (FS) relationship means a successor task cannot begin until its predecessor has finished, which applies to both “Task A starts after Task B finishes” and “Task C must be completed before Task D can start.” The third dependency, “Task E can start when Task F starts,” is a Start-to-Start (SS) relationship, where both tasks can begin simultaneously. On the CompTIA Project+ PK0-005 exam, you will often see these dependency types tested in scenario-based questions that require you to identify the correct relationship from plain-language descriptions. A common trap is confusing FS with SS when the wording uses “after” or “when,” so focus on whether the trigger is the finish or the start of the predecessor. Remember the mnemonic: “Finish-to-Start is the classic handoff; Start-to-Start means they kick off together.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is developing the project schedule. Dependencies include: Task A starts after Task B finishes; Task C must be completed before Task D can start; Task E can start when Task F starts. Which dependency types are being used?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

FS, FS, SS

Option A is correct because the three dependency types described map exactly to Finish-to-Start (FS), Finish-to-Start (FS), and Start-to-Start (SS). 'Task A starts after Task B finishes' is FS; 'Task C must be completed before Task D can start' is also FS; 'Task E can start when Task F starts' is SS. These are the standard dependency definitions used in project scheduling per PMI guidelines.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • FS, FS, SS

    Why this is correct

    First two are FS, third is SS.

    Related concept

    Read the scenario before looking for a memorised answer.

  • SS, SS, SS

    Why it's wrong here

    Only the last is SS.

  • FS, FS, SF

    Why it's wrong here

    SF is Start-to-Finish, not applicable.

  • FS, FF, SS

    Why it's wrong here

    FF is Finish-to-Finish, not used.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse 'starts after finishes' with Start-to-Start (SS) or Start-to-Finish (SF), failing to recognize that 'starts after' implies the predecessor must finish first, which is the definition of Finish-to-Start (FS).

Detailed technical explanation

How to think about this question

In project scheduling, dependency types define the logical relationship between tasks. FS is the most common, used for sequential tasks where the successor cannot start until the predecessor finishes. SS allows parallel execution, often used for overlapping phases (e.g., design and coding). A subtle behavior: SS can have a lag or lead time applied, such as 'Task E starts 2 days after Task F starts,' which is still an SS dependency with a positive lag. Real-world scenario: in software development, testing (Task E) might start when coding (Task F) begins, using SS to enable early defect detection.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: FS, FS, SS — Option A is correct because the three dependency types described map exactly to Finish-to-Start (FS), Finish-to-Start (FS), and Start-to-Start (SS). 'Task A starts after Task B finishes' is FS; 'Task C must be completed before Task D can start' is also FS; 'Task E can start when Task F starts' is SS. These are the standard dependency definitions used in project scheduling per PMI guidelines.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.