PK0-005 Tools and Documentation Practice Question
An agile team uses a burnup chart to track progress. Which THREE pieces of information are typically shown on a burnup chart?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Total work scope line
A burnup chart shows the total work planned (scope line), the actual completed work over time (completed line), and the time remaining (time axis). Remaining work is shown on a burndown chart, not burnup. Velocity is a metric, not a line on the chart.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Total work scope line
Why this is correct
The scope line shows the total amount of work planned.
- ✗
Velocity
Why it's wrong here
Velocity is a metric, not typically plotted on a burnup chart.
- ✗
Remaining work
Why it's wrong here
Remaining work is shown on a burndown chart, not burnup.
- ✓
Time
Why this is correct
Time is represented on the horizontal axis.
- ✓
Completed work over time
Why this is correct
The completed work line shows progress.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.