A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Hybrid

Hybrid combines predictive for overall plan and agile for flexible parts. Predictive would be too rigid; agile lacks upfront plan; iterative may not suit construction.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Agile

    Why it's wrong here

    Agile is too flexible and lacks upfront planning for construction.

  • Hybrid

    Why this is correct

    Correct. Hybrid allows for flexible design iterations within an overall structured plan.

  • Scrum

    Why it's wrong here

    Scrum is an agile framework; same limitations as agile.

  • Predictive (waterfall)

    Why it's wrong here

    Predictive is rigid and does not allow for flexibility in design.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.