PK0-005 Project Management Concepts Practice Question
A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Hybrid
Hybrid combines predictive for overall plan and agile for flexible parts. Predictive would be too rigid; agile lacks upfront plan; iterative may not suit construction.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Agile
Why it's wrong here
Agile is too flexible and lacks upfront planning for construction.
- ✓
Hybrid
Why this is correct
Correct. Hybrid allows for flexible design iterations within an overall structured plan.
- ✗
Scrum
Why it's wrong here
Scrum is an agile framework; same limitations as agile.
- ✗
Predictive (waterfall)
Why it's wrong here
Predictive is rigid and does not allow for flexibility in design.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.