A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

8.33 days

PERT expected duration = (Optimistic + 4*Most Likely + Pessimistic) / 6 = (5 + 4*8 + 13)/6 = (5+32+13)/6 = 50/6 ≈ 8.33 days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 8.0 days

    Why it's wrong here

    That is the most likely, not the expected.

  • 8.33 days

    Why this is correct

    Correct PERT calculation.

  • 7.5 days

    Why it's wrong here

    This is incorrect calculation.

  • 9.0 days

    Why it's wrong here

    This is incorrect.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.