Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To break down the project scope into smaller, manageable components

A WBS decomposes the project scope into manageable work packages, forming the basis for estimating, scheduling, and controlling work.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To break down the project scope into smaller, manageable components

    Why this is correct

    The WBS hierarchically decomposes scope into work packages.

  • To identify project risks

    Why it's wrong here

    Risks are identified in the risk register, not primarily through the WBS.

  • To create the project schedule

    Why it's wrong here

    The schedule is built from the WBS, but the WBS itself is not the schedule.

  • To assign resources to tasks

    Why it's wrong here

    Resource assignment occurs after the WBS is created.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.