PK0-005 Tools and Documentation Practice Question
During a sprint review, the team notes that the remaining work is not decreasing as expected. Which agile artefact would best help visualize the trend of remaining work over the sprint duration?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Burndown chart
A burndown chart shows remaining work over time in a sprint, making it easy to spot deviations from the plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Kanban board
Why it's wrong here
A Kanban board shows work in progress but does not provide a time-based trend of remaining work.
- ✓
Burndown chart
Why this is correct
Correct. A burndown chart tracks remaining work throughout the sprint.
- ✗
Burnup chart
Why it's wrong here
A burnup chart shows completed work over time, not remaining work.
- ✗
Velocity chart
Why it's wrong here
Velocity measures story points per sprint, not remaining work within a sprint.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.