Courseiva
Tools and DocumentationmediumMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

During a sprint review, the team notes that the remaining work is not decreasing as expected. Which agile artefact would best help visualize the trend of remaining work over the sprint duration?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Burndown chart

A burndown chart shows remaining work over time in a sprint, making it easy to spot deviations from the plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Kanban board

    Why it's wrong here

    A Kanban board shows work in progress but does not provide a time-based trend of remaining work.

  • Burndown chart

    Why this is correct

    Correct. A burndown chart tracks remaining work throughout the sprint.

  • Burnup chart

    Why it's wrong here

    A burnup chart shows completed work over time, not remaining work.

  • Velocity chart

    Why it's wrong here

    Velocity measures story points per sprint, not remaining work within a sprint.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.