mediumMultiple SelectObjective-mapped
PK0-005 Practice Question: A project manager is reviewing the project…
A project manager is reviewing the project management plan. Which two components should be included? (Select TWO).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule baseline
The project management plan includes baselines (scope, schedule, cost) and subsidiary management plans. The risk register, issue log, and stakeholder register are project documents.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule baseline
Why this is correct
The schedule baseline is an essential part of the project management plan.
- ✗
Issue log
Why it's wrong here
The issue log is a project document, not a component of the project management plan.
- ✗
Risk register
Why it's wrong here
A risk register is a project document that details identified risks, their analysis, and planned responses. While it is a crucial output of the risk management process and regularly reviewed by a project manager, it is not a component *of* the project management plan itself. The project management plan contains subsidiary plans, such as the *risk management plan*, which describes *how* risks will be managed. The risk register is a separate, dynamic project document, making it tempting as a vital artefact, but distinct from the overarching project management plan.
- ✓
Scope baseline
Why this is correct
The scope baseline is a key component of the project management plan.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is a separate register, not part of the project management plan.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.