easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project manager is assigned to a project that…
A project manager is assigned to a project that has already been chartered. The project sponsor has provided the project charter and initial budget. The project manager is now in the planning phase. During the first planning meeting, the team identifies a major risk: a key supplier may go out of business before the project ends. The project manager needs to proceed. Which of the following is the NEXT step?
⚠ Common exam trap
Watch out — candidates often confuse immediate action (Option A) with proper risk management, or they think escalation (Option D) is always required for major risks, when in fact the risk register is the correct first step per PMI methodology.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Add the risk to the risk register and develop a response plan.
The project manager is in the planning phase, and the first step when a risk is identified is to formally document it in the risk register. After adding the risk, the team should analyze it and develop a response plan. This aligns with the PMBOK Guide's risk management process, which requires recording risks before taking action.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Immediately switch to an alternative supplier.
Why it's wrong here
This is a drastic action without proper analysis of alternatives.
- ✗
Continue planning and address the risk later.
Why it's wrong here
Delaying risk response increases exposure.
- ✓
Add the risk to the risk register and develop a response plan.
Why this is correct
Formal risk management begins with documentation and planning.
- ✗
Escalate the risk to the sponsor for decision.
Why it's wrong here
The project manager can handle this risk without escalation.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.