Courseiva
Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A project manager learns that a key supplier will deliver a critical component three weeks late because of a raw material shortage at the supplier's factory. The project manager immediately notifies the sponsor, contacts two alternate vendors for quotes, and begins revising the schedule to reflect a possible slip. Which risk response strategy is the project manager applying?

⚠ Common exam trap

Many candidates confuse any proactive risk work with avoidance, when avoidance would remove the risky scope entirely rather than reduce its impact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Mitigate

Mitigation lowers the probability or impact of an identified threat. Contacting alternate vendors and revising the schedule to absorb a possible delay directly reduces the impact of the supplier's late delivery, while notifying the sponsor maintains transparency. The risk remains active, so the response cannot be avoidance, transfer, or acceptance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Avoid

    Why it's wrong here

    Avoidance eliminates the threat entirely by changing the project plan, such as removing the component or canceling that scope. Here the component is still required and the threat of delay remains, so the manager is not removing the risk source but actively reducing its impact through alternatives.

  • ✗

    Accept

    Why it's wrong here

    Acceptance means acknowledging the risk and taking no proactive action unless it occurs, possibly with a contingency reserve. Because the manager is contacting alternate vendors and revising the schedule, proactive steps are clearly underway, so passive acceptance is not the strategy in play.

  • ✓

    Mitigate

    Why this is correct

    Mitigation reduces the probability or impact of a threat. By notifying the sponsor, sourcing alternate vendors, and reworking the schedule to absorb a potential slip, the manager is lowering the impact of the supplier delay while the risk is still live, which is the defining behavior of mitigation.

  • ✗

    Transfer

    Why it's wrong here

    Transfer shifts the financial consequence of a threat to a third party, usually through insurance, warranties, or fixed-price contracts. The manager here is not shifting liability to another party but instead actively working to reduce the delay's effect, so transfer does not describe the actions taken.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.