Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget.

CPI = EV/AC = 50000/60000 = 0.83. A CPI less than 1 indicates the project is over budget. The project is spending more than planned for the work performed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget.

    Why this is correct

    Correct. CPI < 1 means over budget.

  • The project is under budget.

    Why it's wrong here

    Under budget would be CPI > 1.

  • The project is getting $1.20 worth of work for every $1 spent.

    Why it's wrong here

    That would be CPI = 1.2, not 0.83.

  • The project is getting $0.83 worth of work for every $1 spent.

    Why this is correct

    Correct. CPI indicates the efficiency of cost performance.

  • The project is on schedule.

    Why it's wrong here

    CPI does not measure schedule performance; SPI does.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.