hardMultiple ChoiceObjective-mapped
PK0-005 A project is behind schedule Practice Question
A project is behind schedule. The project manager decides to start the next phase before the previous phase is fully complete, overlapping activities. This technique is known as:
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Fast-tracking
Fast-tracking overlaps sequential activities, which increases risk but may compress schedule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Resource leveling
Why it's wrong here
Leveling adjusts schedule based on resource constraints.
- ✓
Fast-tracking
Why this is correct
Correct definition.
- ✗
Monte Carlo simulation
Why it's wrong here
Simulation is for analysis, not compression.
- ✗
Crashing
Why it's wrong here
Crashing adds resources, not overlap.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.