Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 A project is behind schedule Practice Question

A project is behind schedule. The project manager decides to start the next phase before the previous phase is fully complete, overlapping activities. This technique is known as:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Fast-tracking

Fast-tracking overlaps sequential activities, which increases risk but may compress schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Resource leveling

    Why it's wrong here

    Leveling adjusts schedule based on resource constraints.

  • Fast-tracking

    Why this is correct

    Correct definition.

  • Monte Carlo simulation

    Why it's wrong here

    Simulation is for analysis, not compression.

  • Crashing

    Why it's wrong here

    Crashing adds resources, not overlap.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.