Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project team uses a tool that displays columns such as 'To Do', 'In Progress', and 'Done' to visualize workflow. This is an example of which type of board?

⚠ Common exam trap

Watch out — candidates often confuse a Scrum board with a Kanban board because both use 'To Do / In Progress / Done' columns; the exam expects you to recognize that the generic continuous-flow board is Kanban, while Scrum boards are sprint-specific.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Kanban board

A Kanban board is a visual workflow management tool that uses columns representing stages of a process (typically 'To Do', 'In Progress', and 'Done') to show the status of work items. It emphasizes continuous flow and limiting work-in-progress (WIP), and is a core artifact in Kanban methodology. The column-based layout described in the question is the defining characteristic of a Kanban board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Pareto chart

    Why it's wrong here

    A Pareto chart is a bar-and-line graph ranking causes by frequency to highlight the vital few, not a workflow visualisation. It tempts because it is a project quality tool, but it addresses defect prioritisation, whereas a Kanban board is the artefact whose columns represent workflow states such as To Do, In Progress and Done.

  • ✗

    Gantt chart

    Why it's wrong here

    A Gantt chart plots tasks against a calendar timeline with durations and dependencies, not workflow-stage columns. It tempts because it also visualises project work, but it answers scheduling questions, whereas a Kanban board is the artefact whose columns represent workflow states such as To Do, In Progress and Done.

  • ✗

    Scrum board

    Why it's wrong here

    A Scrum board tracks sprint backlog items for a Scrum team, so its columns map to sprint work, not a generic continuous workflow. It tempts because the three columns resemble Scrum board layouts, but a Kanban board is the artefact defined by visualising workflow stages such as To Do, In Progress and Done.

  • ✓

    Kanban board

    Why this is correct

    Kanban boards use columns representing workflow states, such as 'To Do', 'In Progress' and 'Done', with cards moving between them. This matches the tool described, satisfying the stem's requirement to identify the board type visualising workflow stages.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.