mediumMultiple ChoiceObjective-mapped
PK0-005 Practice Question: After a change request is approved by the Change…
After a change request is approved by the Change Control Board, what must be updated to reflect the approved changes? (Choose the best answer.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The project plan and baselines
Approved changes must be reflected in the project management plan and baselines (scope, schedule, cost) to maintain accurate control.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The issue log
Why it's wrong here
The issue log tracks problems, not approved changes.
- ✗
Only the risk register
Why it's wrong here
The risk register may be updated but is not the primary document for change implementation.
- ✗
The stakeholder register
Why it's wrong here
Stakeholder register is not typically updated for each change.
- ✓
The project plan and baselines
Why this is correct
Correct. The project plan and baselines are updated to incorporate approved changes.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.