Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: After a change request is approved by the Change…

After a change request is approved by the Change Control Board, what must be updated to reflect the approved changes? (Choose the best answer.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project plan and baselines

Approved changes must be reflected in the project management plan and baselines (scope, schedule, cost) to maintain accurate control.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The issue log

    Why it's wrong here

    The issue log tracks problems, not approved changes.

  • Only the risk register

    Why it's wrong here

    The risk register may be updated but is not the primary document for change implementation.

  • The stakeholder register

    Why it's wrong here

    Stakeholder register is not typically updated for each change.

  • The project plan and baselines

    Why this is correct

    Correct. The project plan and baselines are updated to incorporate approved changes.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.