PK0-005 Project Management Concepts Practice Question
A software development team uses short, time-boxed iterations, daily stand-up meetings, and a prioritized backlog. Requirements are expected to evolve throughout the project. Which project management methodology is being used?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Agile
Agile methodology uses iterative development, time-boxed sprints, daily stand-ups, and adaptive planning. Scrum is a common agile framework with these characteristics.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Agile
Why this is correct
Correct. Agile uses iterative cycles, daily stand-ups, and adaptive planning.
- ✗
Predictive
Why it's wrong here
Predictive (waterfall) uses sequential phases and fixed requirements.
- ✗
Hybrid
Why it's wrong here
Hybrid combines predictive and agile elements, but the description is purely agile.
- ✗
Waterfall
Why it's wrong here
Waterfall is a predictive methodology with sequential phases.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.