PK0-005 Project Management Concepts Practice Question

A project manager is closing out a data-center migration. During the final review, the team discovers that two servers were decommissioned without the required security wipe, which is a compliance violation. The project manager documents the issue and assigns an owner and due date. Which process is the project manager performing?

⚠ Common exam trap

The trap here is treating any defect as a quality-control activity, when the specific act of logging an open problem with an owner and due date is issue management.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Manage Project Issues

The scenario shows a live problem being recorded, assigned an owner, and given a due date so it can be driven to resolution. That is the definition of issue management. Quality control may have detected the defect, and change control may later authorize remediation, but the act of logging and tracking the open problem itself is performed in Manage Project Issues.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Manage Project Issues

    Why this is correct

    Manage Project Issues is the process of identifying, logging, assigning, and driving project issues to resolution, including owners and due dates. The compliance violation is an active problem threatening the project, and the project manager is doing exactly that: documenting it, assigning accountability, and setting a target date for closure.

  • ✗

    Perform Integrated Change Control

    Why it's wrong here

    Perform Integrated Change Control reviews and approves or rejects change requests and manages changes to baselines. The security wipe omission is not a requested change to scope, schedule, or cost, so no change request is being processed. Logging and assigning an issue owner is issue management, not change control, even though a resulting fix might later trigger a change request.

  • ✗

    Control Quality

    Why it's wrong here

    Control Quality monitors and records results of quality activities to assess performance and recommend corrective actions. It is tempting here because the missing security wipe looks like a quality defect. However, the scenario describes the broader act of identifying, logging, and tracking a project issue to closure, which is handled by a dedicated issue-management process rather than quality control alone.

  • ✗

    Manage Project Knowledge

    Why it's wrong here

    Manage Project Knowledge concerns capturing, storing, and reusing lessons and information to benefit the organization. Recording the compliance violation with an owner and due date is corrective action tracking, not knowledge capture. While a lesson may eventually be recorded, the immediate activity of logging and assigning a defect for resolution belongs to a different process.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.