Courseiva
Project Management ConceptshardMultiple SelectObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project manager is closing a project that delivered a new customer relationship management system. Which THREE activities are part of the closing process? (Select THREE).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Release project resources

Closing activities include obtaining formal acceptance, releasing resources, and archiving project documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Release project resources

    Why this is correct

    Releasing resources (team, equipment) is a key closing activity.

  • Create a detailed project schedule

    Why it's wrong here

    Creating a schedule is part of planning, not closing.

  • Obtain formal acceptance of deliverables from the customer

    Why this is correct

    Formal acceptance confirms deliverables meet requirements and closes the project.

  • Conduct a post-implementation review

    Why this is correct

    A post-implementation review evaluates project success and captures lessons learned.

  • Develop the project charter

    Why it's wrong here

    Developing the project charter occurs during initiation, not closing.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.