Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During which project phase is the project charter created and the project manager officially assigned?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating

The project charter is created during the Initiating phase, which formally authorizes the project and assigns the project manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executing

    Why it's wrong here

    Executing involves performing the work.

  • Planning

    Why it's wrong here

    Planning develops the project management plan, not the charter.

  • Initiating

    Why this is correct

    Correct: The charter is created in Initiating.

  • Monitoring and Controlling

    Why it's wrong here

    Monitoring and Controlling tracks progress.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.