Project Life Cycle →easyMultiple Choice

PK0-005 Project Life Cycle Practice Question

During which project phase is the project charter created and the project manager officially assigned?

⚠ Common exam trap

PK0-005 often tests the confusion between the Initiating and Planning phases, as some candidates think the charter is created during planning when detailed scope is defined.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Initiating

The project charter is created and the project manager is officially assigned during the Initiating phase. This phase formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. It is the first phase in the project lifecycle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executing

    Why it's wrong here

    Executing delivers the work defined in the charter and baseline, so authorisation and assignment predate it. It is tempting because the project manager is most visible during execution, and would be correct for questions about acquiring the team, managing stakeholder engagement, or implementing approved changes.

  • ✗

    Planning

    Why it's wrong here

    The charter and project manager assignment occur during initiation, before planning begins; planning produces subsidiary documents like the scope baseline and schedule. Planning is tempting because it is the phase where most project documentation is authored, and would be correct for questions asking where the work breakdown structure or communications plan is created.

  • ✓

    Initiating

    Why this is correct

    Initiating is where the project charter is authorised and the project manager is formally assigned. This phase defines the project's high-level scope and secures organisational approval before planning begins, directly satisfying the stem's requirement for charter creation and PM appointment.

  • ✗

    Monitoring and Controlling

    Why it's wrong here

    Monitoring and Controlling tracks performance against the approved baseline, so the charter already exists and the project manager was assigned earlier. It is tempting because this phase generates change requests and status reports, and would be correct for questions about measuring variance, controlling scope, or approving corrective actions.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.