PK0-005 Project Life Cycle Practice Question
During project closing, which THREE activities should be performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Obtain formal acceptance from the sponsor
Closing includes formal acceptance, lessons learned, and archiving documents. Resource leveling occurs during planning/execution; risk identification occurs during planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Obtain formal acceptance from the sponsor
Why this is correct
Part of project closing.
- ✗
Perform resource leveling
Why it's wrong here
Done during planning/execution.
- ✓
Archive project documents
Why this is correct
Part of project closing.
- ✓
Conduct lessons learned
Why this is correct
Part of project closing.
- ✗
Identify risks
Why it's wrong here
Done during planning.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.