During project closing, which TWO activities are typically performed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Archive project documents

Project closing includes formal acceptance from the sponsor and archiving project documents. Releasing resources is also part of closing, but it's one of the two correct answers here.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the risk register

    Why it's wrong here

    Risk register updates occur throughout the project.

  • Create the project charter

    Why it's wrong here

    The charter is created during initiating.

  • Archive project documents

    Why this is correct

    Correct: archiving is part of closing.

  • Develop the WBS

    Why it's wrong here

    WBS is developed during planning.

  • Obtain formal acceptance from the sponsor

    Why this is correct

    Correct: formal acceptance is a key closing activity.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.