PK0-005 Project Life Cycle Practice Question
During project closing, which TWO activities are typically performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Archive project documents
Project closing includes formal acceptance from the sponsor and archiving project documents. Releasing resources is also part of closing, but it's one of the two correct answers here.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the risk register
Why it's wrong here
Risk register updates occur throughout the project.
- ✗
Create the project charter
Why it's wrong here
The charter is created during initiating.
- ✓
Archive project documents
Why this is correct
Correct: archiving is part of closing.
- ✗
Develop the WBS
Why it's wrong here
WBS is developed during planning.
- ✓
Obtain formal acceptance from the sponsor
Why this is correct
Correct: formal acceptance is a key closing activity.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.