PK0-005 Project Management Concepts Practice Question

A project team is adding extra features to a deliverable that were not requested by the customer, in an effort to improve the product. This practice is known as:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Gold plating

Gold plating is when the project team adds extra features beyond the agreed requirements, often without approval. It can lead to increased cost and schedule overruns.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Benchmarking

    Why it's wrong here

    Benchmarking compares practices to industry standards.

  • Value engineering

    Why it's wrong here

    Value engineering optimizes value without adding unnecessary features.

  • Gold plating

    Why this is correct

    Correct. Gold plating is adding extras not required by the customer.

  • Scope creep

    Why it's wrong here

    Scope creep is uncontrolled changes to scope, but gold plating is adding extra features voluntarily.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.