Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000 and the actual cost (AC) is $150,000. What is the estimate at completion (EAC) using the typical cost performance index (CPI) assumption?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$250,000

EAC = BAC / CPI. CPI = EV/AC = $120,000/$150,000 = 0.8. Thus, EAC = $200,000 / 0.8 = $250,000.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $170,000

    Why it's wrong here

    This might be from subtracting the variance, but EAC formula typically uses CPI.

  • $300,000

    Why it's wrong here

    This would be BAC / (EV/BAC) or similar miscalculation.

  • $250,000

    Why this is correct

    Correct. EAC = BAC / CPI = $200,000 / 0.8 = $250,000.

  • $230,000

    Why it's wrong here

    This is not derived from standard EAC formulas.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.