Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?

⚠ Common exam trap

PK0-005 often tests the confusion between analogous (single comparable project, top-down) and parametric (statistical formula with unit rates) estimation, since both rely on historical data — candidates must identify whether a formula or a single reference project is being used.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimation

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project's cost, then adjusts for known differences in size, complexity, or scope. This is exactly what the project manager is doing — referencing actual costs of a comparable project and scaling them. It is a top-down, expert-judgment-driven technique that is fast but less accurate than detailed methods.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Parametric estimation

    Why it's wrong here

    Parametric estimation applies a statistical relationship between cost and a measurable driver, such as cost per function point, rather than adjusting one analogous project's actual cost. It is tempting because both use historical data, and would be correct when a reliable unit rate and quantifiable parameter are available.

  • ✗

    Three-point estimation

    Why it's wrong here

    Three-point estimation uses optimistic, pessimistic, and most likely values to calculate a weighted average, but the scenario describes adjusting a single past project’s actual cost for size and complexity differences—this is the mechanism of analogous estimation, not three-point. The option is tempting because three-point estimation also incorporates historical data and uncertainty, and would be correct if the project manager had multiple estimates from past tasks requiring a probabilistic range rather than a single adjusted baseline.

  • ✗

    Bottom-up estimation

    Why it's wrong here

    Bottom-up estimation sums individual work package or task costs to build the total, so it never starts from a past project's actual cost. It is tempting because it also produces a defensible figure, and would be correct when detailed task-level data exists and a granular, auditable estimate is required.

  • ✓

    Analogous estimation

    Why this is correct

    Analogous estimation derives cost from the actual cost of a comparable historical project, then scales it for differences in size and complexity. This top-down, experience-based approach matches the scenario, unlike parametric or bottom-up methods that build estimates from component detail.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.