Courseiva
Project Life Cycle →hardMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?

⚠ Common exam trap

Many exam-takers confuse CPI with SPI or inverting the numerator and denominator — candidates who memorize 'EV over something' without anchoring which denominator belongs to which index will pick 0.83 (SPI) or 1.10 (AC/EV) instead of 0.91.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

0.91

CPI is calculated as EV divided by AC. With EV = $50,000 and AC = $55,000, CPI = 50,000 / 55,000 = 0.909, which rounds to 0.91. A CPI below 1.0 indicates the project is over budget for the work performed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    0.83

    Why it's wrong here

    A CPI of 0.83 divides EV by AC incorrectly, using PV ($60,000) as the denominator instead of AC. It is tempting because schedule performance index (SPI) is calculated as EV/PV, yielding 0.83 here; that formula answers how efficiently schedule is being used, not cost.

  • ✗

    1.10

    Why it's wrong here

    1.10 inverts the CPI formula, dividing PV by AC rather than EV by AC. The tempting error is treating the index as a schedule measure; a value above 1.0 signals under-budget spending, which would arise only if EV exceeded AC. Here EV of $50,000 against AC of $55,000 gives 0.91.

  • ✓

    0.91

    Why this is correct

    CPI is earned value divided by actual cost: 50,000 divided by 55,000 equals approximately 0.91. A value below 1.0 indicates the project is over budget for the work completed, since each dollar spent delivered only about 91 cents of earned value.

  • ✗

    1.20

    Why it's wrong here

    CPI is EV divided by AC, giving 50,000/55,000, approximately 0.91, so 1.20 is wrong. The value 1.20 would result from dividing EV by PV (the schedule performance index), which measures schedule efficiency rather than cost efficiency.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.